Communication to BUYERS of construction services

The Association strongly urges Buyers to consider adopting our recommended escalation clause based on the American ConsensusDocs 200.1 Amendment “Potentially Time & Price Impacted Materials”, as amended here, be adopted in all upcoming construction procurements.
CLICK HERE to download the OCA recommended escalation clause which is an amended ConsensusDocs 200.1.

Let us explain why, if we may:

Allocation of Risk for Hyperinflation

Obviously, the tender documents, including the contract drafted by your organization and in particular its payment terms, are used as a means to allocate the burden of delivery risk and incentivise the contractor to deliver to time and quality. The form of contract (fixed price vs. cost plus for example) and its payment terms and the approach to risk allocation go hand-in-hand. The aim of the payment terms and pricing structure is to reflect the optimum balance between risk and return in the contract for you as owner/buyer. As a general principle, the approach should be to link payment to the delivery of service outputs and the performance of the contractor.

Where a risk is transferred to the contractor, such as one relating to price and thus hyperinflation, the price paid by the owner reflects this and there is no adjustment mechanism if the event (hyperinflation / price escalation) does occur and impacts the contractor’s cost base (because it has already priced in the risk of the event occurring).

Where a risk (e.g. hyperinflation risk) is not transferred (or not wholly transferred) to the contractor, contractual mechanisms can exist to adjust the price paid to the contractor by the owner by adjusting the price, or elements of the price, linked to a specified index.

With current contract language laying bare the risk of hyperinflation on the contractor, contractors are managing the risk of hyperinflation by:

  1. Carrying a contingency in their bid prices (negative impact on owner/buyer);
  2. Pre-purchase of material (neutral impact – but not overly available);
  3. Qualifying bid submissions (negative impact on owner/buyer);
  4. Making claims for price increase after contract award (negative impact on owner/buyer).

As a result, how can we as industry participants, address the allocation of hyperinflation risk so that it is shared risk and ensuring that the owner/buyer is getting value.

A price escalation mechanism may be such a mechanism.

Price Adjustment Clauses

Generally, a material price adjustment clause will entitle a contractor to a change order where the price of certain types of materials increases either between the time of bid submission or the time the contract is effective and when the contractor orders the material.  The amount of additional compensation the contractor can seek or the owner may claim (if a commodity price has gone down) may be based on either the actual price of the material versus the amount included in the bid or by using a commodity index to calculate the increased amount.

The shortcoming in many price adjustment clauses is that there is no corresponding mechanism where price indexes show price decreases. We have tried to address that below.

What are ConsensusDocs?

ConsensusDocs documents are a series of form contracts, akin to CCDC or CCA standard form documents, that drafted, compiled and distributed by a group of organizations that represent contractors and other players in the construction industry in the U.S. The contract documents this group has developed are called ConsensusDocs because a series of trade organizations representing general contractors, sub-contractors and other construction professionals, came together and reached a consensus on what should be included in these standard form contracts in a way that will overcome some of the shortcomings that they saw in other standard form contracts.

What is ConsensusDocs 200.1?

ConsensusDocs 200.1 Amendment No. 1- Potentially Time and Price-Impacted Materials and Schedule A, is a good resource for drafting price escalation clauses.

Under this document, parties identify potentially time and price-impacted materials and establish a method for establishing a baseline price based upon market or catalog prices, actual material costs, material cost indices or some other mutually agreed upon method. This document provides for an agreed upon percentage adjustment to the contract price for increases or decreases in the baseline price, excluding overhead and profit, provided the contractor provides written notice and appropriate documentation substantiating such adjustment. It also provides that the contractor shall be entitled to an equitable extension of contract price and an equitable adjustment of the contract price for the delay in the delivery of, or unavailability of, a potentially time and price-impacted material beyond the control of and without the fault of the contractor or downstream party.

Recommended Material Price Index

The OCA Is recommending referencing the United States Department of Labour Producer Price Index Table 9 (https://www.bls.gov/web/ppi/ppitable09.pdf) for any construction material. This index was selected due to its superiority to any Canadian index as to its extensive list of materials and the monthly tracking of cost changes.

Example Utilization of Escalation Clause

In the bidding stage, drywall is identified as a material experiencing hyperinflation and is agreed upon between the Buyer and Prime Contractor to be addressed with this price escalation clause. The baseline amount for drywall at time of contract is $400,000. Contract signed January 2022 and it agreed that the date of adjustment will be when the drywall is purchased 5 months later in May 2022.

Baseline Price = $400,000

PPI Commodity Code for Gypsum is #13-7101 of US Dept of Labour PPI

PPI Index as of January 2022 is 417.482

PPI Index as of May, 2022 is 450.113

Difference is 450.113 – 417.482 = 32.631  which in percentage terms 32.631 divided by 417.482 = 7.81 %

Price Adjustment = $400,000 x 7.81 % = $31,240

Adjustment Provision

With the foregoing and the attached, the Ottawa Construction Association, is proposing a price adjustment provision to be included in your tender documents to help share the risk associated with certain commodity prices. We believe the attached is relatively balanced in that credits can be claimed by the owner/buyer if there is a decrease in certain commodity items identified by the contractor at time of bid.

We urge you to consider including a price adjustment provision in your upcoming tender documents which will benefit you in obtaining more competitive pricing given that contingencies will not be required or if required will be greatly reduced in a corresponding reduction in claims.

More NewsView All News & Press Releases

March 19, 2024

OCA Elects Hubie Splinter 2024 Chair
The Ottawa Construction Association is pleased to announce that the members of its Board of Directors have elected Hubie Splinter, President of Graebeck Construction as its 2024 Chair.

Read More about OCA Elects Hubie Splinter 2024 Chair

March 24, 2023

Congratulations Coffrages Synergy Formwork Recipient of the CCA 2023 Excellence in Innovation Award
The CCA Excellence in Innovation Award recognizes outstanding CCA member firms who have implemented innovative construction practices within the past two years. These practices must have been a “first-time” use or adoption for use in Canada, but may have been previously applied or used elsewhere. The recipient is awarded with the Hugh R. Montgomery Memorial Trophy, which commemorates the life and work of Hugh R. Montgomery, a past president of CCA who gave generously of his time and experience for the general well-being of the industry.

Read More about Congratulations Coffrages Synergy Formwork Recipient of the CCA 2023 Excellence in Innovation Award

March 24, 2023

Congratulations – Russell Grass Sr.Recipient of the2023 CCA Community Leader Award
The CCA Community Leader Award recognizes CCA member firms, partner associations or individuals employed by a CCA member firm who have devoted time and effort to the betterment of their communities.

Read More about Congratulations – Russell Grass Sr.Recipient of the2023 CCA Community Leader Award